Challenge Week 29

Which of the following demand fulfillment approaches typically provides the longest delivery time?

Answer A) Engineer-to-order
(B) make-to-order
(C) assemble-to-order
(D) make-to-stock

Challenge Week 30

Which of the following is generally a characteristic of a product-focused layout?

((A) large queues at workstations
Answer (B) fixed flow of work
(C) production to a work order
(D) general purpose workstations

Challenge Week 31

Which of the following represents the pace of production synchronized with the rate of sales?

A) poka-yoke
Answer (B) takt
(C) continuous flow
(D) production leveling

Challenge Week 32

Daily operating time divided by required quantity per day is a calculation of which of the following?

((A) cycle time
(B) process time
Answer (C) takt time
(D) lead time

Challenge Week 39

Owner’s equity is

(A) revenue less liabilities
(B) revenue less expenses
Answer (C) assets less liabilities
(D) assets less expenses

Challenge Week 41

In most cases, the fastest way to increase capacity to meet a short-term requirement is to

(A) hire additional workers
Answer (B) use overtime
(C) acquire more equipment
(D) subcontract work

Challenge Week 45

The demand at a workstation in a lean system typically comes from

Answer (A) a pull signal
(B) a dispatch list
(C) the production plan
(D) a control chart